Construction of a new transformer centre and transfer of the existing one to the Paterna Science Park

Construction of a new transformer centre, transfer of the existing one and legalisation of their corresponding new medium and low voltage lines.
Progress of the performance











Start date
March 21st, 2024
Completion date
June 27th, 2024
Budget
€129,139.71
Licensing dossier
213/2022/2757
Issuing a licence
25/06/2024
Location
Authors of the project and project management
- Bosch Fayos, Juan Antonio
- CPS Infraestructures, Mobilitat i Medi ambient
- Dupuy Alamo, Montserrat
- CPS Infraestructures, Mobilitat i Medi ambient
Construction company
Elecnor Servicios y Proyectos S.A.
UV Responsible
Technical Unit