Intervention in Rector Peset Hall of Residence. Skylight replacement and refurbishment of the Miramar Tower
Rehabilitation Rehabilitation
 

The project is split in two parts.

Skylight replacement. The work will consist of removing the polycarbonate canopy over the original skylight to be able to remove its glass panes and the secondary structure on which they rest. The auxiliary means deemed necessary will be used.

Miramar Tower. The work to be carried out on the tower is concentrated on its upper part. From the cornice to the top. The grouting on the solid brick wall in that last part of the tower is degrading and needs to be replaced with lime mortar. Similarly, the finish of the cornices is deteriorating and would also need to be replaced. The dome with the exterior copper plate finish must be replaced and the interior wood that makes up the inside of the dome must be treated or replaced, if necessary. The grouting on the bricks of this last section of the tower must be replaced where necessary, as well as the stones that make up its highest part.

Cupola finial. The cupola finial is completely fractured due to the expansion of the metallic element, probably still inside it. Its dismantlement is needed to treat or substitute the metallic element and then put it back in again, with an exterior waterproofing treatment. For the intervention on the Miramar Tower and the top cupola, it is proposed to carry out vertical works.

Progress of the performance
Authorisation of the expenditure by the University Head Office and the Office of the Vice-Principal for Economy and InfrastructuresAuthorisation of the expenditure by the University Head Office and the Office of the Vice-Principal for Economy and Infrastructures
Preparation of the technical specifications (PPT)Preparation of the technical specifications (PPT)
Preparation by the SCA of the table of characteristics annexed to the specific administrative clauses (PCAP) and revision of the PPTPreparation by the SCA of the table of characteristics annexed to the specific administrative clauses (PCAP) and revision of the PPT
Call for tenders for the design and management of the projectCall for tenders for the design and management of the project
Decision to award the project designDecision to award the project design
Preparation of the project designPreparation of the project design
Application for building permitApplication for building permit
Tender for the workTender for the work
Signing of the contractSigning of the contract
Start of the workStart of the work
Handover stageHandover stage
Start date May 1st, 2021
Completion date August 1st, 2021
Budget

€143,648.17 (VAT included).

Licensing dossier E03501/2022/4453
Location

Manteniu premuda la tecla Ctrl mentre us desplaceu per apropar o allunyar el mapa

Authors of the project and project management
  • Carratalá Calvo, Luis
  • Arquitecte
Construction company

Cypsa

UV Responsible
Technical and Maintenance Service

Blasco Ibáñez Campus

Av. Blasco Ibañez, 13

46010 Valencia (Valencia)

+34 963 864 205

+34 963 983 479

https://www.uv.es/stecnic

servei.tecnic@uv.es